Welcome Guest
  |   0 items in your shopping cart
 

BROWSE BY STANDARDS

BROWSE BY CATEGORY

***
 
 
Join our mailing list to recieve newsletters
 

FIDIC Users' Guide : A Practical Guide to the 1999 Red and Yellow Books, 2nd Edition

Send to friend
 
Title: FIDIC Users' Guide : A Practical Guide to the 1999 Red and Yellow Books, 2nd Edition
Author: B. W. Totterdill
ISBN: 0727734415 / 9780727734419
Format: Hard Cover
Pages: 408
Publisher: ICE Publishing
Year: 2006
Availability: Out of Stock
     
 
  • Description
  • Contents

The FIDIC Conditions of Contract for Construction and the Conditions of Contract for Plant and Design-Build (known as the '1999 Red Book' and the '1999 Yellow Book') were first published in 1999 and have been used for a large number of contracts around the world. During 2005, FIDIC and the multilateral development banks cooperated to publish the MDB Harmonised Conditions of Contract for Construction. This book is a revised and extended edition of the author's earlier guides.

Part 1 : The Traditional and the 1999 FIDIC Conditions of Contract
Chapter 1 :
Introduction to the FIDIC Conditions of Contract
Chapter 2 : Comparisons between the different FIDIC Conditions of Contract
Chapter 3 : The 1999 FIDIC Red and Yellow Books
Chapter 4 : Claims and dispute procedures
Chapter 5 : Flow charts

Part 2 : The FIDIC Conditions of Contract for Construction and for Plant and Design-Build
Chapter 6 :
Introduction to Part 2
Chapter 7 : Contents : General Conditions
Chapter 8 : Definitions listed alphabetically
Chapter 9 : Clause 1 : General Provisions
Chapter 10 : Clause 2 : The Employer
Chapter 11 : Clause 3 : The Engineer
Chapter 12 : Clause 4 : The Contractor
Chapter 13 : Clause 5 (RB) : Nominated Subcontractors
Chapter 14 : Clause 5 (YB) : Design
Chapter 15 : Clause 6 : Staff and Labour
Chapter 16 : Clause 7 : Plant, Materials and Workmanship
Chapter 17 : Clause 8 : Commencement, Delays and Suspension
Chapter 18 : Clause 9 : Tests on Completion
Chapter 19 : Clause 10 : Employer's Taking Over
Chapter 20 : Clause 11 : Defects Liability
Chapter 21 : Clause 12 (RB) : Measurement and Evaluation
Chapter 22 : Clause 12 (YB) : Tests after Completion
Chapter 23 : Clause 13 : Variations and Adjustments
Chapter 24 : Clause 14 : Contract Price and Payment
Chapter 25 : Clause 15 : Termination by Employer
Chapter 26 : Clause 16 : Suspension and Termination by Contractor
Chapter 27 : Clause 17 : Risk and Responsibility
Chapter 28 : Clause 18 : Insurance
Chapter 29 : Clause 19 : Force Majeure
Chapter 30 : Clause 20 : Claims, Disputes and Arbitration

Part 3 : Appendices
Appendix 1 :
General Conditions of Dispute Adjudication Agreement
Appendix 2 : Annex : Procedural Rules
Appendix 3.1 : Index of Sub-Clauses in the Conditions of Contract for Construction
Appendix 3.2 : Index of Sub-Clauses in the Conditions of Contract for Plant and Design-Build
Appendix 4 : Annexes and Forms

Part 4 : MDB Harmonised Edition of the FIDIC Conditions of Contract for Construction
Chapter 31 :
The MDB Edition

Part 5 : Sub-Clause comparison
Chapter 32 :
A comparison of Sub-Clause numbers between the fourth edition of ‘The Red Book’ and the 1999 Conditions of Contract for Construction

Index

 
 
 
About Us | Contact us
loading...
This page was created in 0.19012594223022 seconds